Andrew Jackson Elementary School - Parking Lot Improvements

  • Description: Repair and repaving of the traffic lane (where necessary) in the Jackson Elementary parking lot.
  • Bid Opening Date:  March 20, 2025
  • Date BOE Funding Approved:  March 11, 2025
  • Approved Construction Cost:  $92,305.32 + engineering fees and contingency 
  • Funding Source: General Purpose School Fund Unreserved Fund Balance
  • Contractor:  Brown Brothers Paving, LLC
  • Anticipated Completion Date:  Summer 2025
  • Approval Documentation
 

project update

4/10/25: Bid has been awarded to Brown Brothers Paving, LLC.  Work expected to begin once school is out for the summer.