Dobyns-Bennett High School - Renovation Project

  • Description:  Renovation of D-B interior and exterior spaces, including replacement of hallway, ramp, and classroom flooring, interior painting, removal of existing lockers, replacement of exterior stairs, restructuring of the current Annex Pod into new classroom spaces, and other identified items.   
  • Bid Opening Date:  May 8, 2026
  • Date BOE Approved:  May 12, 2026
  • Approved Project Cost:  $3,269,384
  • Funding Source:  Dobyns-Bennett Renovation Project GP2111
  • Contractor:  Construction Partners
  • Anticipated Completion Date:  Winter 2026
  • Approval Documentation
 

project update

7/24/26:  Completed interior work in academic pods (English, Math, Social Studies) includes flooring of pods and ramps, painting of hallways and classrooms.  Demolition of Annex pod continues.
5/26/26:  Interior project begins, including demolition of flooring and lockers in academic pods (English, Math, Social Studies).  Demolition of exterior stairs behind Math pod.
5/12/26:  Bid approved by the Kingsport Board of Education.