9/15/23: Project complete. Sprankle Gymnasium installation and painting/striping complete.
8/18/23: Main gym floor refinishing and repainting is complete. Sprankle Gymnasium floor leveling process has been completed and subfloor has been installed. New floor is currently being laid.
4/28/23: It is anticipated that demolition work on the existing Sprankle Gymnasium floor will begin as early as the week of May 15, 2023. Refinishing of the Main Gymnasium floor will begin once additional wall painting work is complete, expected in early June.