Capital Projects » D-B EXCEL - Expansion and Renovation

D-B EXCEL - Expansion and Renovation

  • Description: Provide necessary life and safety upgrades to unfinished spaces adjacent to the D-B EXCEL facility, allowing for lab-type use by students during the school day.
    • Includes area behind current DBE cafeteria space and large storage area connecting to main hallway.
    • Work to include fire-rating existing unfinished walls and adding necessary egress doorways, exit signage, electrical outlets, and data outlets.
  • Bid Opening Date:  March 30, 2023
  • Date BOE Approved:  April 11, 2023
  • Approved Project Cost:  $196,225
  • Funding Source: School Capital Improvements Project, GP2301
  • Contractor:  Comsa Construction
  • Completion Date:  August 2023
  • Approval Documentation
 

project update

8/25/23: Project Complete.
4/28/23: Work will take place that allows, per code, for students to occupy currently undeveloped spaces during the school day for lab-type activities.