Description: Provide necessary life and safety upgrades to unfinished spaces adjacent to the D-B EXCEL facility, allowing for lab-type use by students during the school day.
Includes area behind current DBE cafeteria space and large storage area connecting to main hallway.
Work to include fire-rating existing unfinished walls and adding necessary egress doorways, exit signage, electrical outlets, and data outlets.
Bid Opening Date: March 30, 2023
Date BOE Approved: April 11, 2023
Approved Project Cost: $196,225
Funding Source: School Capital Improvements Project, GP2301
4/28/23: Work will take place that allows, per code, for students to occupy currently undeveloped spaces during the school day for lab-type activities.