project update
7/31/23: Project substantially complete.
4/28/23: Utilizing a construction schedule one week in length, construction is taking place in a rotational fashion, with two classrooms having their HVAC system replaced each week. Currently, approximately 50% of classrooms have had their old units replaced. This rotation will continue until the 2022-23 school year is complete. At that time, construction crews will utilize the summer months to complete the replacement project.