Capital Projects » Andrew Jackson Elementary School - Boiler Replacement

Andrew Jackson Elementary School - Boiler Replacement

  • Description:   Replace existing boiler due to it's reaching end-of-life.  Work to include:
    • Demolition and removal of existing boiler
    • Installation of new boiler
  • Bid Opening Date:  August 23, 2023
  • Date BOE Approved:  September 12, 2023
  • Approved Project Cost:  $96,346
  • Funding Source:  Current operating budget capital improvement account
  • Contractor:  Premier Boiler & Combustion, LLC
  • Anticipated Completion Date:  Fall 2023
  • Approval Documentation
 

project update

12/11/23:  Project complete.
 
9/29/23:  Replacement of existing boiler expected to take place over Fall Break 2023.
 
9/12/23: Project approved by BOE.  Pre-construction meeting to take place to determine final construction schedule.