Capital Projects » Johnson Elementary School - HVAC Replacement

Johnson Elementary School - HVAC Replacement

  • Description:  Replacement of HVAC units in classrooms and common areas of Johnson Elementary School.  Replaces all units, as they are approaching their end-of-life. 
  • Bid Opening Date:  November 7, 2023
  • Date BOE Approved:  November 14, 2022
  • Approved Project Cost:  $3,499,860
  • Funding Source:  General Project Fund
  • Contractor:  S.B. White Company, Inc.
  • Anticipated Completion Date:  Summer 2024
  • Approval Documentation
 

project update

4/19/24:  First unit installation has taken place this week.  The first units were installed on a two-week schedule (as planned) so the contractor can learn and address any issues with the demolition of the previously installed units and the install of the new units.  Future units will be installed on a one-week schedule.
 
3/22/24:  Ongoing site prep work taking place in advance of equipment arrival.  Initial HVAC equipment arrival scheduled for arrival in the next two weeks.  Anticipated first installations to take place in mid-April.  Initial installation schedule established with contractor and school administration.
 
3/15/24:  Scheduling of construction plan underway, identifying expected dates for HVAC replacement in specific rooms/locations.  Currently awaiting arrival of HVAC equipment.
 
2/29/24:  HVAC equipment ordered and awaiting arrival.  Expected to occur near Spring Break.
 
12/18/23:  Pre-construction meeting with contractor has taken place, outlining the general project approach and to ensure procedural steps are understood and underway.  Materials and equipment will be ordered, with construction beginning once delivery occurs.  Initial work pre-delivery will take place as able. 

project Photos