Ross N. Robinson Middle School - HVAC Replacement

  • Description:  Replacement of HVAC units in classrooms and common areas of Jefferson Elementary School.  Work to include:
    • Replace all units, as they are approaching their end-of-life
  • Bid Opening Date:  May 2, 2023
  • Date BOE Approved:  May 9, 2023
  • Approved Project Cost:  $3,089,280
  • Funding Source:  ESSER 3.0
  • Contractor:  S.B White Company, Inc.
  • Anticipated Completion Date:  Summer 2024
  • Approval Documentation
 

project update

8/15/24:  Project substantially complete.  Addressing individual issues if/when they occur.
 
7/12/24:  Project walkthrough took place on 7/11 to review progress and identify remaining areas of need.  Project nearing completion.  Minimal work items remaining, with project completion prior to the start of the school year on-schedule.
 
5/30/24:  Workload volume increasing due do building being empty for summer vacation.  Installation of classroom units taking place.
 
5/17/24:  Classroom installations taking place.  Acceleration of installation process to occur once school lets out for the summer.
 
4/19/24:  Installation of units continuing as scheduled.  Monitoring and adjusting of newly installed units taking place as-needed.  Planning for summer work taking place in coordination with school administration and staff.
 
3/22/24:  Installation of units continuing as scheduled.
 
3/15/24:  HVAC replacement continuing throughout the building.  Project still on-schedule for completion late Summer 2024.
 
2/29/24: HVAC replacement cycle occurring throughout the building.  Project on-schedule for completion late Summer 2024.
 
5/9/23: Project approved by BOE.  Pre-construction meeting to take place to determine final construction schedule.